Halo, Simpson St, Manchester Construction Update
22nd January 2018
All on track at Halo !
Our site at Simpson St, Manchester is once again in full swing after the Christmas break as we are now enter week 40 of the 82 week programme.
The basement is now complete and the concrete frame has been extended to the ground floor level.
Metal frame and flooring to the first floor level is 80% complete and brickwork infill to the ground floor has been finished. Work now continues on the steel frame erection and frame panels and concrete infill to piles.
Halo on track for Delivery October 2018