Construction Latest Update Halo

17th October 2018

Construction on Halo, our Manchester city residential development in Simpson Street in the heart of Ancoats, is progressing ever onwards as purchasers look forward to delivery later this year.

Scaffolding on the top floor has been dismantled as the glass balconies are put in place as installation work continues further down the lower floors.
main scaffold scaffold

balcony3 balcony 4

balcony2 balcony

Internal fixtures and fittings continue through the building with kitchens and bathrooms taking shape.
fitted kichen fridge

Kitchens with quality silestone worktops come fully equipped with oven, hob, extractor and top-branded appliances.

fridge shower bathroom fittings

Fully tiled bathrooms and ensuite shower rooms with high quality sanitary ware complement the luxury city life style.

Whilst behind the scenes, plumbing, water tanks, boilers and electrics are all well underway as mains connections have been switched on.
hotwater cyclinder electric meter

The front door with access from Simpson Street into the main reception and lobby area is in place as well as the lift supporting the additional stair wells.

front door lift2

Whilst below ground the basement parking and vehicular ramps are ready to offer residents secure city parking.

carpark carpark entrance

As contractors crank up the overtime to push works ahead, we are now regularly welcoming mortgage valuers on site as clients line up their finance and begin ordering their furniture with scheduled delivery just around the corner.