Construction continues at Halo, our off-plan apartments in Simpson Street, revitalising and opening the northern area of Manchester city centre. All works are progressing within programme and despite the inclement weather the whole team are confident that the development will be completed on schedule.

The metal framework for all floors is now complete.
Halo Simpson St steel floor joists

Halo steel wall frames

The sixth floor is now built and the building is now watertight.
Halo Roof

Halo Simpson St, Manchester

Internal plasterboard walls are now in excess of 50% complete.
workman internal walls

Halo 5th Floor

Windows and external brickwork are currently at 65%.
Brickwork & windows

First fix Mechanical and Electrical works are being carried out on four floors.Halo Simpson St Electrics