Construction Latest News, Halo

10th April 2018

The metal frame work for the fifth storey floor at Halo is now in place with concrete shortly to be poured at our high profile residential development in Simpson Street, Manchester.

Halo 5th floor stairs

Halo Construction update

The final 6th floor will then be added to top out the building.

Brick facing walls at Halo

Internal walls with plaster board and external brick facings are being fitted working up the building.

Halo under construction

Internal walls at Halo

Electrical and mechanical fittings are being planned and positioned.

Electrical Fittings Halo

All looking good at Halo and with all homes sold, Forshaw are on track for delivery of the 66 apartments in October later this year. Another market-leading product for vibrant Manchester city living.

View current buy-to-let off-plan investment opportunities.