September 2019, Worrall St Construction Update

It’s been a busy summer since the existing building has been demolished and the land where  The Waterhouse will eventually stand.  

Since the last update, we’ve turned the entire site over to ensure that there are no obstructions in the soil. Our remediation contractor (Forshaw Demolition) has then compacted the soil in layers ensuring that the ground is ready to receive and support our building. Our main contractor has taken possession of the site and the piling rig is there now driving the concrete piles deep into the ground, these will be what the building stands upon when construction is completed, the cabins are in place and the perimeter fencing to the road is now up too.

There is a couple of weeks piling ahead of us before we can start pouring concrete, which will be the next update.

Piling Rig 2

Construction Update, Worrall Street

Remediation works and site preparation continue at our riverside site at Worrall St, Salford as a precursor to the commencement of ground works shortly.


Construction Update, Worrall St

After manually stripping off the roof last week, the “boys with their toys” arrived on site this week and quickly made their mark as the heavy machinery swung into action at Worrall St, Salford.

The job’s a good ‘un.

The existing brick building now demolished allows surveys and ground works to commence over the coming months for delivery of 86 new build high specification waterside apartments due for completion 2020.

With pre-sales well under way, there are still some river fronting units available. View more details here or just complete the contact form below to receive a comprehensive brochure and floor plans.

Contact Form

"*" indicates required fields


Construction Update, on Worrall Street – Manchester

Our Remediation Strategy for our Worrall Street site in Salford was approved last week by the council. We are now permitted to conduct environmental studies and take the required soil samples for analysis prior to construction.

The demolition company has been appointed and the demolition of the existing brick structure is now underway.

The Worrall St site fenced off with demolition now starting.
The existing building to be demolished to provide 86 new build waterfront apartments.
The first crews arrived on site this week.
The roof has to be manually removed prior to the larger demolition machinery arriving.
The internal fittings area also ripped out prior to demolition of the brick structure.

Works are set to continue over the next two weeks, with demolition of the existing building and remediation of the site to allow ground works to commence shortly.

With a growing population, Manchester and Salford are undergoing significant urban regeneration programmes which have led to a thriving local economy and bouyant rental market. Whether you’re a new or seasoned investor find out more about our fully-managed residential investment opportunities.